46 results, showing 1 to 10
Under NBN Co’s Special Access Undertaking, NBN Co must lodge its proposed set of Accounting Procedures with the ACCC by 31 March 2024 (or the next business day). NBN Co provided its submission on 2 April 2024.
On 31 May 2023, the ACCC commenced a combined public inquiry to decide whether to extend, revoke, vary the following 9 declarations or whether to allow them to expire.
The Australian Rail Track Corporation has provided its indicative Constrained Coal Customer Unders and Overs Estimate and True-Up Test Audit report for 2021, ahead of its formal annual compliance submission (expected in late 2022).
The 2011 Hunter Valley Coal Network Access Undertaking (HVAU) requires the Australian Rail Track Corporation (ARTC) to send documents to the ACCC for an annual compliance assessment. As part of this assessment, we examine ARTC's operating costs, including overheads.
The 2011 Hunter Valley Coal Network Access Undertaking (HVAU) requires the Australian Rail Track Corporation (ARTC) to submit documentation to the ACCC for the purpose of an annual compliance assessment. The 2022 annual compliance assessment will be carried out in accordance with Schedule J of version 8 of the HVAU.
ARTC submitted its annual compliance documentation for calendar years 2019 and 2020 to the ACCC for assessment on 26 November 2021.
The Migration Plan sets out the steps that Telstra will take to progressively migrate voice and broadband services from its copper and Hybrid Fibre Coaxial networks to the NBN.
On 20 December 2021 the ACCC wrote to Port of Portland Limited (POPL) regarding its 2021-22 bulk grain export capacity allocation process and non-compliance with subclause 25(2) of the Port Terminal Access (Bulk Wheat) Code of Conduct.
On 30 July 2021 the ACCC commenced a public inquiry, under Part 25 of the Telecommunications Act 1997, into the declared wholesale asymmetrical digital subscriber line (WADSL) service. The ACCC has released a Consultation and position paper to facilitate its inquiry.
On 10 August 2021, the ACCC released a final determination for the period 1 January to 31 December 2018. The ACCC's final determination is that ARTC's revised submission from 17 June 2021 is in accordance with all requirements under the HVAU. The submitted true-up test audit is also in accordance with HVAU requirements.