39 results, showing 1 to 10
The Australian Rail Track Corporation has provided its indicative Constrained Coal Customer Unders and Overs Estimate and True-Up Test Audit report for 2021, ahead of its formal annual compliance submission (expected in late 2022).
ARTC submitted its annual compliance documentation for calendar years 2019 and 2020 to the ACCC for assessment on 26 November 2021.
On 10 October 2022 the ACCC sent a letter to ARTC regarding the potential timing of assessing a replacement undertaking. On 19 December 2022 ARTC provided a letter to stakeholders outlining its intent to submit a new 2023 IAU and a further extension of the 2008 IAU in early 2023.
The ACCC is reviewing the regulatory framework for ARTC's Interstate network.
The ACCC is required under Part 6 of the Water Charge Rules 2010 (WCR) to decide whether on-river infrastructure operators meet the definition of ‘Part 6 operators’ and, if so, whether to grant them an exemption from the operation of the requirements of Part 6 of the WCR.
The ACCC is required under Part 6 of the Water Charge Rules 2010 (WCR) to decide whether on-river infrastructure operators meet the definition of ‘Part 6 operators’ and, if so, whether to grant them an exemption from the operation of the requirements of Part 6 of the WCR.
The ACCC is required under Part 6 of the Water Charge Rules 2010 (WCR) to decide whether on-river infrastructure operators meet the definition of ‘Part 6 operators’ and, if so, whether to grant them an exemption from operation of the requirements of Part 6 of the WCR.
The ACCC is required under Part 6 of the Water Charge Rules 2010 (WCR) to decide whether on-river infrastructure operators meet the definition of ‘Part 6 operators’ and, if so, whether to grant them an exemption from operation of the requirements of Part 6 of the WCR.
On 23 April 2020, the ACCC engaged GHD to conduct a Depreciated Optimised Replacement Cost (DORC) valuation of ARTC's Interstate network to determine the Regulated Asset Base (RAB).
On 10 August 2021, the ACCC released a final determination for the period 1 January to 31 December 2018. The ACCC's final determination is that ARTC's revised submission from 17 June 2021 is in accordance with all requirements under the HVAU. The submitted true-up test audit is also in accordance with HVAU requirements.