On 25 September 2013, the ACCC accepted the revised undertaking provided by Emerald on 9 September 2013.
Emerald revised undertaking
On 9 September 2013, Emerald withdrew its 26 March undertaking and submitted a revised undertaking for consideration by the ACCC. The revised undertaking was consistent with the draft revision earlier provided by Emerald on 31 July 2013.
Document title | Published date |
---|---|
20130909 Emerald letter to ACCC re Revised Undertaking ( PDF 110.54 KB ) | 26 September 2013 |
20130909 Emerald Revised Port Terminal Services Access Undertaking ( PDF 1.14 MB ) | 26 September 2013 |
ACCC decision to accept
The ACCC decided on 25 September 2013 to accept the revised undertaking provided by Emerald on 9 September 2013. The reasons for the ACCC's decision are set out in the decision document.
Document title | Published date |
---|---|
20130926 ACCC decision to accept Emerald's 2013 Access Undertaking ( PDF 356.95 KB | DOCX 129.54 KB ) | 26 September 2013 |
20130926 ACCC letter to Emerald re acceptance of 2013 Undertaking ( PDF 314.11 KB ) | 26 September 2013 |