On 31 March 2014 NBN Co wrote to the ACCC to advise that it would not meet its obligations under the SAU to publish 3-Year and 1-Year Construction Rollout Plans by 31 March 2014. NBN Co has advised the ACCC that it will use its best endeavours to publish these plans as soon as possible.
Submissions in response to NBN Co's letter were due by Wednesday 9 April 2014.
On 4 July 2014, NBN Co confirmed to the ACCC that there is still not a sufficiently robust basis on which it can prepare the rollout plans, and that it is continuing to use its best endeavours to provide these plans as soon as possible.
On 1 December 2014, NBN Co made its 18-month rollout information forecast available.
Rollout progress
Document title | Published date |
---|---|
NBN Co SAU - Letter - Rollout progress information - March 2014 ( PDF 418.43 KB ) | 2 April 2014 |
NBN Co SAU - ACCC letter to NBN Co - Rollout progress information - April 2014 ( PDF 209.47 KB ) | 2 April 2014 |