Regulatory projects

Title Industry Type Status
Extension of the 2008 Interstate Access Undertaking (to February 2019) Rail Undertaking variation Submissions due
4 December 2018

On 16 November 2018 ARTC submitted an application to vary its 2008 Interstate Access Undertaking by two months until 28 February 2019.

On 20 November 2018 the ACCC sent a letter to stakeholders seeking comments on ARTC's proposal. Submissions are due by 4 December 2018.

September 2018 variation of the 2011 Hunter Valley Access Undertaking Rail Access variation Under assessment
28 September 2018

On 28 September 2018, ARTC applied to the ACCC to vary its 2011 Hunter Valley Access Undertaking. The variation seeks to change a number of provisions in the undertaking, including:

December 2017 variation of the 2011 Hunter Valley Access Undertaking Rail Access variation Withdrawn
27 July 2018

On 21 December 2017, ARTC applied to the ACCC to vary its 2011 Hunter Valley Access Undertaking. The variation seeks to change a number of provisions in the undertaking, including:

  • incorporating path based pricing
  • allocating incremental capital costs on the basis of contracted capacity
  • applying a dual ceiling limit.

ARTC's application and its supporting materials are available below.

Extension of the 2008 Interstate Access Undertaking (to December 2018) Rail Undertaking variation Accepted
25 July 2018

On 28 June 2018 ARTC submitted an application to vary its 2008 Interstate Access Undertaking by four months until 21 December 2018.

On 3 July 2018 the ACCC sent a letter to stakeholders seeking comments on ARTC's proposal. Submissions were due by 17 July 2018.

On 25 July 2018 the ACCC consented to ARTC's variation application.

Interstate Rail access undertaking 2018 Rail Access undertaking Under assessment

On 2 March 2018, ARTC lodged a replacement undertaking for the interstate rail network. This undertaking is to replace ARTC's 2008 undertaking, which expires 31 August 2018. The access undertaking covers the terms and conditions of access for parties seeking to run trains on the mainline standard gauge rail track owned or leased by ARTC.

Annual compliance assessment 2015 Rail Compliance assessment Under assessment
20 October 2017

The 2011 Hunter Valley Access Undertaking (2011 HVAU) requires ARTC to submit documentation to the ACCC for the purposes of an annual compliance assessment. Section 4.10 and Schedule G of the 2011 HVAU  requires the ACCC to determine whether ARTC has complied with the financial model and pricing principles specified in the undertaking and whether there has been any under or over recovery of revenue from users that needs to be reconciled.

June 2017 variation of the 2011 Hunter Valley Access Undertaking Rail Undertaking variation Accepted
29 June 2017

On 5 June 2017, ARTC applied to the ACCC to vary its 2011 Hunter Valley Access Undertaking to extend the term of the undertaking by four and a half years to 31 December 2020.

ARTC's application and public versions of its supporting materials are available below.

Hunter Valley access undertaking 2017 Rail Access undertaking Withdrawn
8 May 2017

On 9 December 2016, ARTC submitted the 2017 Hunter Valley Access Undertaking (2017 HVAU) to the ACCC for assessment pursuant to Part IIIA of the Competition and Consumer Act 2010. This access undertaking is for the provision of access to the Hunter Valley Rail Network operated by ARTC in New South Wales.

Annual compliance assessment 2014 Rail Compliance assessment Finalised
31 March 2017

The accepted Hunter Valley Access Undertaking requires ARTC to submit documentation to the ACCC for the purposes of an annual compliance assessment.

Extension of the 2011 Hunter Valley Access Undertaking (to June 2017) Rail Undertaking variation Accepted
23 November 2016

On 18 October 2016, ARTC applied to the ACCC to extend the term of its 2011 Hunter Valley Access Undertaking by a further six months to 30 June 2017.

On 19 October 2016, the ACCC sent a letter to industry seeking comments on ARTC's proposal. Submissions were due by 2 November 2016.

On 23 November 2016, the ACCC consented to ARTC's revised variation application.

Extension of the 2011 Hunter Valley Access Undertaking (to December 2016) Rail Undertaking variation Accepted
16 June 2016

On 20 May 2016, ARTC applied to the ACCC to vary its 2011 Hunter Valley Access Undertaking to extend the term of the undertaking by six months to 31 December 2016.

Hunter Valley access undertaking 2016 Rail Access undertaking Withdrawn
15 June 2016

On 23 December 2015, ARTC submitted an access undertaking to the ACCC for assessment pursuant to Part IIIA of the Competition and Consumer Act 2010 (the Act). The access undertaking is in relation to the provision of access to the Hunter Valley Rail Network operated by ARTC in New South Wales.

The ACCC previously accepted an access undertaking on 29 June 2011 in relation to the Hunter Valley Rail Network. The ACCC has approved an extension of the term of the 2011 HVAU to 31 December 2016.

Annual compliance assessment 2013 Rail Compliance assessment Finalised
6 June 2016

The accepted Hunter Valley Access Undertaking requires ARTC to submit documentation to the ACCC for the purposes of an annual compliance assessment. Section 4.10 and Schedule G of the undertaking requires the ACCC to determine whether ARTC has complied with the financial model and pricing principles specified in the undertaking and whether there has been any under or over recovery of revenue from users that needs to be reconciled.

ARTC advices on reviews Rail Access undertaking Finalised
25 Sep 2012

These letters from the ARTC document the progress of various reviews related to the 2011 Hunter Valley undertaking.

 

Tags

Audience