Proposed withdrawal of s87B undertakings relating to the Dampier to Bunbury Natural Gas Pipeline

Acquirer(s)

  • Diversified Utility and Energy Trust (DUET)
  • Babcock and Brown Infrastructure and Babcock and Brown Power
  • Alinta Limited
  • Alinta Network Services Pty Ltd
  • Alcoa of Australia Limited
  • DBNGP Holdings Pty Ltd
  • Epic Energy (WA) Transmission Pty Ltd

Other

Document title Date

Timeline

DateEvent
08/01/2010ACCC commenced review under the Merger Review Process Guidelines.
15/01/2010Closing date for submissions from interested parties.
27/01/2010ACCC requested further information from the parties. ACCC timeline suspended. Former proposed date for announcement of ACCC's findings, of 27 January 2010, amended to allow parties to respond to information request.
22/02/2010ACCC received further information from the parties. ACCC timeline recommenced.
31/03/2010ACCC requested further information from the parties. Former proposed date for announcement of ACCC's findings, of 31 March 2010, amended to allow for parties to respond to the ACCC's information request. ACCC timeline suspended.
07/05/2010ACCC received further information from the parties. ACCC timeline recommenced.
09/06/2010ACCC announced it did not consent to the proposed withdrawal of the undertakings.