Summary
The Applicants seek authorisation to discuss, make and give effect to arrangements regarding the sequencing and timing of scheduled maintenance works, and associated shutdowns and outages, at each of their liquefied natural gas facilities in Curtis Island in the Port of Gladstone (LNG Facilities). The proposed conduct seeks to limit the extent to which scheduled maintenance works occur concurrently at the LNG Facilities.
On 18 February 2016, the ACCC issued a draft determination proposing to grant conditional authorisation for five years. The condition of authorisation would require the Applicants to publicly disclose maintenance information that they have shared among themselves.
On 18 February 2016, the ACCC also granted interim authorisation subject to the same condition.
On 14 April 2016, the ACCC granted conditional authorisation for five years. The condition requires the Applicants to publicly disclose maintenance schedule information that they have shared with one another, and to ensure that information remains accurate.
A copy of the ACCC's determination is available from the 'ACCC decisions' link below.
On 18 February 2016, the ACCC issued a draft determination proposing to grant conditional authorisation for five years. The condition of authorisation would require the Applicants to publicly disclose maintenance information that they have shared among themselves.
On 18 February 2016, the ACCC also granted interim authorisation subject to the same condition.
On 14 April 2016, the ACCC granted conditional authorisation for five years. The condition requires the Applicants to publicly disclose maintenance schedule information that they have shared with one another, and to ensure that information remains accurate.
A copy of the ACCC's determination is available from the 'ACCC decisions' link below.
Applicant(s)
- Australia Pacific LNG Pty Ltd
- CNOOC QCLNG Pty Ltd
- CNOOC QCLNG Tolling Pty Ltd
- ConocoPhillips Australia Pty Ltd
- KGLNG Liquefaction Pty Ltd
- PAPL (Downstream) Pty Limited
- QCLNG Common Facilities Company Pty Ltd
- QCLNG Operating Company Pty Ltd
- QCLNG Train 1 UJV Manager Pty Ltd
- QCLNG Train 2 Pty Ltd
- QCLNG Train 2 UJV Manager Pty Ltd
- QGC Pty Ltd
- QGC Train 1 Pty Ltd
- QGC Train 1 Tolling Pty Ltd
- QGC Train 2 Tolling No.2 Pty Ltd
- QGC Train 2 Tolling Pty Ltd
- Santos GLNG Pty Ltd
- Tokyo Gas QCLNG Pty Ltd
- Total GLNG Australia
- Walloons Coal Seam Gas Company Pty Ltd
Authorisation number(s)
- A91516
- A91517
Applications
Document title | Date | |
---|---|---|
Received ( PDF 1.86 MB ) | 15 Oct 2015 |
Decisions
Document title | Date | |
---|---|---|
Final Determination ( PDF 563.56 KB ) | 14 Apr 2016 | |
Draft Determination ( PDF 470.71 KB ) | 18 Feb 2016 |
ACCC correspondence
Document title | Date | |
---|---|---|
ACCC to Interested Parties re Final Determination ( PDF 150.35 KB ) | 14 Apr 2016 | |
ACCC to Applicants re Final Determination ( PDF 152.55 KB ) | 14 Apr 2016 | |
ACCC to Interested Parties re Draft Determination ( PDF 186.02 KB ) | 18 Feb 2016 | |
ACCC to Applicant re Draft Determination ( PDF 193.43 KB ) | 18 Feb 2016 | |
ACCC to Interested Parties re draft condition consultation ( PDF 177.03 KB ) | 19 Jan 2016 | |
Draft Condition annexed to ACCC consultation letter to Interested Parties ( PDF 35.89 KB ) | 19 Jan 2016 | |
ACCC to Interested Parties re Consultation Process ( PDF 288.14 KB ) | 30 Oct 2015 | |
ACCC to Applicants re Interested Party Consultation ( PDF 114.56 KB ) | 30 Oct 2015 | |
Show all documents (5 more) |
Submissions - before draft decision
Document title | Date | |
---|---|---|
Submission by Senex Energy Limited ( PDF 29.7 KB ) | 10 Feb 2016 | |
Stanwell Corporation Limited ( PDF 102.21 KB ) | 1 Feb 2016 | |
ERM Power ( PDF 884.87 KB ) | 1 Feb 2016 | |
Competitive Energy Association ( PDF 166.16 KB ) | 1 Feb 2016 | |
Origin Energy Limited ( PDF 231.32 KB ) | 16 Dec 2015 | |
QGC Pty Limited ( PDF 237.42 KB ) | 30 Nov 2015 | |
Applicants ( PDF 38.2 KB ) | 30 Nov 2015 | |
Monadelphous Group Limited ( PDF 399.28 KB ) | 24 Nov 2015 | |
EnergyAustralia Pty Ltd ( PDF 181.24 KB ) | 23 Nov 2015 | |
Energy Supply Association of Australia ( PDF 101.11 KB ) | 23 Nov 2015 | |
Stanwell Corporation Limited ( PDF 7.17 MB ) | 20 Nov 2015 | |
ERM Power ( PDF 881.78 KB ) | 16 Nov 2015 | |
SVT Engineering Consultants ( PDF 53.01 KB ) | 9 Nov 2015 | |
Show all documents (10 more) |
Submissions - after draft decision
Document title | Date | |
---|---|---|
Response to submissions ( PDF 81.42 KB ) | 4 Apr 2016 | |
Response to Submissions ( PDF 25.81 KB ) | 11 Mar 2016 | |
Submission by Applicants ( PDF 85.25 KB ) | 4 Mar 2016 | |
Submission by Energy Australia ( PDF 122.64 KB ) | 4 Mar 2016 | |
Submission by ERM Power ( PDF 1.44 MB ) | 4 Mar 2016 | |
Submission by Stanwell Corporation Limited ( PDF 112.98 KB ) | 4 Mar 2016 | |
Show all documents (3 more) |