18 results, showing 1 to 10
On 21 February 2023 ARTC submitted an application to extend the term of its 2008 Interstate Access Undertaking to 30 June 2024. This is a 12-month extension from the existing expiration date of 30 June 2023.
On 23 April 2021, ARTC submitted an application to extend the term of its 2008 Interstate Access Undertaking to 30 June 2023.
On 5 May 2020, ARTC submitted an application to vary its 2008 Interstate Access Undertaking. The variation sought to extend the term of the undertaking to 30 June 2021.
On 29 July 2019, ARTC submitted an application to vary its 2008 Interstate Access Undertaking to 30 June 2020.
On 29 January 2019 ARTC submitted an application to vary its 2008 Interstate Access Undertaking.
On 16 November 2018 ARTC submitted an application to vary its 2008 Interstate Access Undertaking by two months until 28 February 2019.
On 28 September 2018, ARTC applied to the ACCC to vary its 2011 Hunter Valley Access Undertaking.
On 28 June 2018 ARTC submitted an application to vary its 2008 Interstate Access Undertaking by four months until 21 December 2018.
On 6 June 2017, ARTC applied to the ACCC to vary its 2011 Hunter Valley Access Undertaking.
On 18 October 2016, ARTC applied to the ACCC to extend the term of its 2011 Hunter Valley Access Undertaking by a further six months to 30 June 2017.
Industry
Status
Type