Proposed variation to the s87B undertakings of Alinta Limited and others dated 25 October 2004
Type of assessment
Variation to Undertakings
Reference
24156
Acquirer(s)
Alinta Ltd Diversified Utility and Energy Trust Alcoa of Australia Ltd Alinta Network Services Pty Ltd DBNGP Holdings Pty Ltd
Target(s)
Epic Energy Pty Ltd
Industry
Gas
Summary
Alinta Asset Management Pty Ltd (AAM), formerly Alinta Network Services Pty Ltd, submitted a draft variation to the s87B undertaking of Alinta Limited and others, which was accepted by the ACCC on 25 October 2004.
The draft variation proposed to remove AAM from the undertaking, because AAM had ceased to be a party to the operating services agreement for the Dampier to Bunbury Natural Gas Pipeline.
Given that the amendments proposed by the AAM Variation have been superseded by the broader variation which was accepted by the ACCC on 28 January 2010, the ACCC has ceased its review of the AAM variation.
Outcome of assessment
No decision
Total review days *
53
Commenced public review
10th June 2009
Date completed
28th January 2010
Undertakings
Draft variation to s87B undertaking 3rd June 2009 D09+60737.pdf (90.4 KB)
Review timeline
Date
Event
10th June 2009
ACCC commenced review under the Merger Review Process Guidelines.
2nd July 2009
ACCC timeline suspended at the request of Alinta Asset Management Pty Ltd.
3rd December 2009
ACCC timeline recommenced at the request of Alinta Asset Management Pty Ltd.
18th December 2009
Closing date for submissions from interested parties.
28th January 2010
ACCC ceased its review of the proposed variation.
* Total Review days = Total business days less public holidays and time during which the review was suspended.